Project Links

City of Crosby Water System Improvements
On Monday, July 12th, the Crosby City Council authorized the Rice Lake Construction Group (Project Contractor) to proceed with construction of the Crosby Water System Improvements, which will include the following construction activities:
The tentative plan by the Project Contractor is to begin to mobilize equipment and materials on Monday, July 26th. The first anticipated construction activity planned would be clearing and grubbing of trees along the proposed construction path. This work is tentatively scheduled to begin the week of August 2nd.
Once construction commences, weekly construction updates will be prepared and submitted for posting on this website to provide information about project progress and schedules for pending project activity. The project is planned to be substantially completed by August 15, 2011.