TH 25 ARRA Reconstruction Project

Project Schedule
May, 2010 – Approximate start of project. Begin detours.
July 1, 2010 – Substantial Completion. TH 25 and all intersections are to be open to traffic.
July 31, 2010 – Final Completion.