Project Schedule
What to Expect the Week of October 15th...
Area 1:
Work on the new trail connection from the end of Cambridge Lane to Brighton Boulevard has been pushed back to 2013 and it will be a 5-foot wide concrete path. The final layer of asphalt (except Manchester Rd. west of Devon Ln.) is scheduled for Thursday and Friday. The storm water infiltration basin at Bradford Road and Monmouth Road is scheduled for this week.
Area 2:
Driveway patching is scheduled for completion this week. Restoration work will commence this week along with retaining wall installation. The two dead-end watermain lines on Kildare Road will be connected using the directional drilling method, but this won't be done until next year.
Area 3:
Driveway patching, manhole adjusting and retaining wall construction are scheduled for this week. Cardiff, Denbigh and Cardigan are scheduled from the final layer of asphalt the week of November 5th.