1st Street - Street & Utility Reconstruction


Project Schedule

Present Preliminary Engineering Report
& Order Public Improvement Hearing ..................................................... December 15, 2008

Conduct Public Improvement Hearing........................................................... January 5, 2009

Order Improvement and Preparation of Plans & Specifications.......................February 2, 2009

Approve Plans & Specifications and Advertise for Bids ..................................... March 2, 2009

Accept Bids / Award Bid................................................................................... April 6, 2009

Construction .................................................................................... May 2009 Ð June 2010

Order Assessment Hearing ...................................................................... To Be Determined

Conduct Public Assessment Hearing/Adopt Assessment Roll ....................... To Be Determined