It is proposed that all construction be completed by October 2007.
Present & Accept Feasibility Report
March 5, 2007
Meet With School Representatives
March 20, 2007
Hold Neighborhood Meeting
March 22, 2007
Hold Public Hearing and Order Plans & Specifications
April 2, 2007
Plan Submittal to State Aid
May 4, 2007
Approve Plans & Specifications
May 14, 2007
Open Bids
June 27, 2007
Award Contract
July 2, 2007
Begin Construction
July 23 2007
Complete Construction
October 31, 2007
Order Preparation of Assessments &
Set Date for Assessment Hearing
November 2007
 |
 |