2007 MSA Project


Project Schedule

It is proposed that all construction be completed by October 2007. 

Present & Accept Feasibility Report
March 5, 2007

Meet With School Representatives
March 20, 2007

Hold Neighborhood Meeting
March 22, 2007

Hold Public Hearing and Order Plans & Specifications
April 2, 2007

Plan Submittal to State Aid
May 4, 2007

Approve Plans & Specifications
May 14, 2007

Open Bids
June 27, 2007

Award Contract
July 2, 2007

Begin Construction
July 23 2007

Complete Construction
October 31, 2007

Order Preparation of Assessments &
Set Date for Assessment Hearing
November 2007