5th Street - Street & Utility Reconstruction


Project Schedule

Neighborhood Meeting #1 (input for design considerations)
May 23, 2006

Ordered Feasibility Report
August 7, 2006

Neighborhood Meeting #2 (discuss preliminary design)
October 19, 2006

Received Feasibility Report and Ordered Public Hearing
November 6, 2006

Adopted Addendum to Feasibility Report
November 20, 2007

Conducted Public Hearing
November 20, 2007

Ordered Preparation of Plans and Specifications
November 20, 2007

Ordered Proposed Assessment and Public Hearing
March 5, 2007

Advertise Public Assessment Hearing – Northfield News
March 14 & 21, 2007

Notices to Residents
March 15, 2007

Approved Plans and Authorize Advertisement
March 15, 2007

Advertise for Bids-Northfield News & Construction Bulletin
March 21, 2007

Assessment Hearing
April 2, 2007

Open Bids
April 12, 2007

Award Project
April 16, 2007

Construction Begins
May, 2007

Construction Completed (except bituminous wear course)
November 15, 2007

Construction of Bituminous Wear Course
Early Summer 2008




Project Summary
Project Overview
Public Meetings
Notices/Newsletters
Project Schedule
Project Maps
Project Contacts
Comments/Public Input

City of Northfield

Client Zone
Home Contact Us Careers Bid Info News Who We Are Services Invoice Payment Client Zone