Public Informational Meeting #1 | September 5, 2019 |
Public Improvement Hearing | September 10, 2019 |
Final Design (Construction Plans) | September 2019 – February 2020 |
Dates below are tentative and are subject to change:
Public Informational Meeting #2 | January 23, 2019 |
Open Bids | March 6, 2020 |
Public Informational Meeting #3 | April 2020 |
Begin Construction | April/May 2020 |
Assessment Hearing | Late October 2020 |
Substantial Completion | Late October 2020 |
Final Completion | June 2021 |