City of Lewiston – 2019 Street & Utility Improvements Project Schedule

Project Schedule

  • Neighborhood Informational Meeting – May 23, 2017
  • Prepare Feasibility Report – October 2017
  • Neighborhood Informational Meeting – November 2, 2017
  • Neighborhood Informational Design Meeting – February 2018
  • Bid Opening – April 5, 2018
  • Neighborhood Informational Meeting – April 2018
  • Award Contract – April 28, 2018
  • Begin Construction – May 2018
  • LRIP Grant Award – Fall 2018
  • Rebidding of Contract – May 2019
  • Construction – July – September 2019
  • End Construction – October 2019