City of Ostrander – Infrastructure Rehabilitation Project Schedule

Project Schedule

  • Project Planning, Funding Applications, and Design – 2013 to 2016
  • Funding Approval for Phase 1 Improvements – August 2016
  • Phase 1 Project Design – August 2016 to January 2018

Phase 1 Project Construction Schedule

CSAH 1 (Main Street) and CSAH 3 (Center Street) Infrastructure Improvements

  • Bid Opening – January 24, 2018
  • Award Contract – February 2018
  • Neighborhood Informational Meeting – February 2018 (Date to be determined)
  • Begin Construction – April 2018
  • End Construction – July 2019

Well & Well House Improvements

  • Bid Opening – February 22, 2018
  • Award Contract – March 2018
  • Begin Construction – Spring 2018
  • End Construction – Winter 2018/2019

Phase 2 Project Schedule

  • To be determined, dependent on additional funding