Project Schedule
- Neighborhood Informational Meeting – November 6, 2019
- Council Meeting to Finalize Project Scope and Authorize Design – November 12, 2019
- Neighborhood Informational Meeting – February 18, 2020 (Tentative)
- Bid Opening – April 9, 2020 (Tentative)
- Award Contract – April 14, 2020 (Tentative)
- Neighborhood Informational Meeting – April 28, 2020 (Tentative)
- Begin Construction – May 2020
- End Construction – June 2021 (All work except final asphalt layer in reconstruction areas complete by October 2020)