Rushford 2019 Street Reconstruction Rushford 2019 Schedule

Schedule

Meeting Notice – 11/1/18
Notice of Hearing – 11/13/18

Meeting Notices
Tentative Project Schedule:
  • Neighborhood Meeting #1         – August 7, 2018
  • Preliminary Design                     – Fall 2018
  • Neighborhood Meeting #2         – November 1, 2018
  • Improvement Hearing                – November 13, 2018
  • Final Design                                – November 2018 – February 2019
  • Neighborhood Meeting #3         – January 23, 2019
  • Open Bids                                  – February 22, 2019
  • Assessment Hearing                   – March 25, 2019
  • Neighborhood Meeting #4         – April 17, 2019
  • Begin Construction                     – Early May 2019
  • Substantial Completion             – September 13, 2019
  • Final Completion                        – June 19, 2020