City of Rushford – TH 30 Reconstruction Website Tentative Schedule

Tentative Schedule

Preliminary Public Meetings
(Round 1, 3 total)

Dec 2019 – Feb 2020

City Council Layout
Discussion

Mar 9, 2020

Geometric Layout &
Feasibility Report 

Apr – Sept 2020

City Council Feasibility
Report Presentation

Sept 14, 2020

Preliminary Public Meetings
(Round 2, 2 total)

Oct 8, 2020 (2:00 PM &
5:30 PM)

Public Improvement Hearing

Oct 13, 2020

Municipal Consent Hearing

Fall 2020 (Date TBD)

Begin Final
Design   

Nov 2020

Public Informational
Meeting (Design) 

Winter 2020/21

Finalize Construction
Plans  

Jul 2021

Bidding    

Jan 2022

Final Assessment Hearing

Feb/Mar 2022

Begin Construction  

Spring 2022

Substantial Completion
(Construction) 

Fall 2022

Final Completion
(Construction)

Spring 2023

Updated 10/6/2020

Named one of the very best workplaces in the State of Minnesota! We’re proud to rank in the Top 50 on the list, and even prouder that we were voted in by our own employees.