City of Rushford – TH 30 Reconstruction Website Tentative Schedule

Tentative Schedule

Updated 5/3/2022

**Construction dates can and will change depending on timing of springtime thaw, weather, delays, and other factors.

 

Preliminary Public Meetings (Round 1, 3 total) Dec 2019 – Feb 2020
City Council Layout Discussion 9-Mar-20
Geometric Layout & Feasibility Report  Apr – Sept 2020
City Council Feasibility Report Presentation 14-Sep-20
Preliminary Public Meetings (Round 2, 2 total) Oct 8, 2020 (2:00 PM & 5:30 PM)
Public Improvement Hearing 13-Oct-20
Begin Final Design    Nov-20
Municipal Consent Hearing April 26 2021 (6:30 pm)
Finalize Construction Plans Nov-21
Bidding Feb 25,-22
Tree Removal Mar 2022
Public Meeting (Assessments/Construction) Apr 26, 2022
Final Assessment Hearing May 9, 2022
Phase 1 Construction (Mill -Stevens) May 9, 2022 – Late July 2022
Phase 2 Construction (Stevens to West End) Early July 2022 – October 2022
Final Completion (Punch List Complete) Spring 2023

Named one of the very best workplaces in the State of Minnesota! We’re proud to rank in the Top 50 on the list, and even prouder that we were voted in by our own employees.