Updated 5/3/2022
**Construction dates can and will change depending on timing of springtime thaw, weather, delays, and other factors.
Preliminary Public Meetings (Round 1, 3 total) | Dec 2019 – Feb 2020 |
City Council Layout Discussion | 9-Mar-20 |
Geometric Layout & Feasibility Report | Apr – Sept 2020 |
City Council Feasibility Report Presentation | 14-Sep-20 |
Preliminary Public Meetings (Round 2, 2 total) | Oct 8, 2020 (2:00 PM & 5:30 PM) |
Public Improvement Hearing | 13-Oct-20 |
Begin Final Design | Nov-20 |
Municipal Consent Hearing | April 26 2021 (6:30 pm) |
Public Meeting (Assessments/Construction) | |
Final Assessment Hearing | May 9, 2022 |
Phase 1 Construction (Mill -Stevens) | May 9, 2022 – Late July 2022 |
Phase 2 Construction (Stevens to West End) | Early July 2022 – October 2022 |
Final Completion (Punch List Complete) | Spring 2023 |