City of Rushford – TH 30 Reconstruction Website Tentative Schedule

Tentative Schedule

Preliminary Public Meetings
(Round 1, 3 total)

Dec 2019 – Feb 2020

City Council Layout
Discussion

Mar 9, 2020

Geometric Layout &
Feasibility Report 

Apr – Sept 2020

City Council Feasibility
Report Presentation

Sept 14, 2020

Preliminary Public Meetings
(Round 2, 2 total)

Oct 8, 2020 (2:00 PM &
5:30 PM)

Public Improvement Hearing

Oct 13, 2020

Begin Final
Design

Nov 2020

Municipal Consent Hearing

April 26th 2021 (6:30 pm)

Public Informational
Meeting (Design) 

Spring 2021

Finalize Construction
Plans  

Jul 2021

Bidding    

Jan 2022

Final Assessment Hearing

Feb/Mar 2022

Begin Construction  

Spring 2022

Substantial Completion
(Construction) 

Fall 2022

Final Completion
(Construction)

Spring 2023

Updated 3/8/2021