City of Rushford – TH 30 Reconstruction Website Tentative Schedule

Tentative Schedule

Updated 5/3/2022

**Construction dates can and will change depending on timing of springtime thaw, weather, delays, and other factors.

 

Preliminary Public Meetings (Round 1, 3 total)Dec 2019 – Feb 2020
City Council Layout Discussion9-Mar-20
Geometric Layout & Feasibility Report Apr – Sept 2020
City Council Feasibility Report Presentation14-Sep-20
Preliminary Public Meetings (Round 2, 2 total)Oct 8, 2020 (2:00 PM & 5:30 PM)
Public Improvement Hearing13-Oct-20
Begin Final Design   Nov-20
Municipal Consent HearingApril 26 2021 (6:30 pm)
Finalize Construction PlansNov-21
BiddingFeb 25,-22
Tree RemovalMar 2022
Public Meeting (Assessments/Construction)Apr 26, 2022
Final Assessment HearingMay 9, 2022
Phase 1 Construction (Mill -Stevens)May 9, 2022 – Late July 2022
Phase 2 Construction (Stevens to West End)Early July 2022 – October 2022
Final Completion (Punch List Complete)Spring 2023