  • Neighborhood Informational Meeting – May 11, 2017
  • Prepare Feasibility Report – September 2017
  • Neighborhood Informational Meeting – October 19, 2017
  • Improvement Hearing – October 23, 2017
  • Neighborhood Information Design Meeting – January 30, 2018
  • Bid Opening – March 7, 2018
  • Neighborhood Informational Meeting – April 2018
  • Award Contract – April 2018
  • Assessment Hearing – April 2018
  • Begin Construction – May 2018
  • End Construction – October 2018 [all work except final wearing course and punch list, which will be completed in June 2019]