Runway 13/31 Improvements, City of Litchfield, Minnesota
Using the FDR process allowed the City to reconstruct the runway, taxiway, and apron within the amount of Federal funding available.

Runway 13/31 Improvements

City of Litchfield, Minnesota

Runway 13/31, Taxiway A, and the apron pavement were in dire need of reconstruction due to severe longitudinal and transverse cracking, rutting, depressions, and patching. Fully reconstructing all pavements in one year was not feasible because of limited federal funding.

Bolton & Menk designed and constructed a full-depth reclamation (FDR) project to rejuvenate the airport's pavement. FDR is the process of pulverizing the existing bituminous, then blending the pulverized mixture and blending with the underlying aggregate base to provide a recycled bituminous base course. FDR recycles existing materials on-site while providing a comparable product to virgin aggregate base at a substantially lower price.

Using the FDR process allowed the city to reconstruct the runway, taxiway, and apron within the federal funding amount available.

Award logo

Awards

  • Award 1 MnDOT Office of Materials & Road Research – 2016 Merit Award for Bituminous Surfacing