2017 Sidewalk Improvement Project

Project Summary

April 10, 2017

The Complete Streets Committee met on April 7, 2017 to make a recommendation on which side of the street the sidewalks will be placed on Del Matro Avenue, 64th Street and Northwest Drive.  The locations of the sidewalks will be as follows:

  • Del Matro Avenue – South side of the street
  • 64th Street – East side of the street
  • Northwest Drive – North side of the street
  • 63rd Street – West side of the street

The recommendation was based on safety, connectivity, cost and constructability. The design team has begun final design on these four locations.


Project Locations

Project Status & Updates

May 24, 2017

Currently the Project is out for bid to prospective bidders with bid opening June 8th.  If Council awards the bids, Construction can begin in early July.  A definite schedule will not be known until a Contractor is hired.
 

March 20, 2017

Survey crews are currently collecting field data and will continue to do so for the next week (weather permitting).

Contacts

Justin L Ernst P.E.

Project Engineer
Phone: 515-259-9190

 

Matthew W Ferrier P.E.

Principal Project Manager
Phone: 515-259-9190

Future Meetings